Surface Paving on Bentgrass, Boomerang, Gullwing, and Up & Over


To:  All Owners and Residents of Bentgrass, Boomerang, Gullwing, Up and Over
RE:  Lennar Asphalt Surface Paving
When:  November 11th, 12th, 13th 
Inclement weather dates are November 14th & 15th

Please let this email serve as Lennar’s notice to perform base asphalt repairs as directed by Harford County, and then immediately follow up with the installation of the final surface course of asphalt. All homeowners must NOT park on the roadways during this time frame. Please park on your driveways. If you have more vehicles then the driveway holds, you may temporarily parking vehicles at the clubhouse parking lot.

Please review the attached documents for maps of the sections of streets affected by the asphalt surface paving work.

Work Schedule:

November 11th

  • Base repairs will commence starting in section “D,” Bentgrass Drive, then working our way towards the intersection of Up & Over Way and Bentgrass Drive where sections “A”, “B,” and “D” all meet.
  • We will continue base repairs from the intersection of Up & Over Way and Bentgrass Drive to the intersection of Up & Over Way and Boomerang Way in section “A,” including base repairs in Boomerang Way.
  • Continuing with the base repairs from the intersection of Up & Over Way and Boomerang Way in section “A” to the intersection of Up & Over Way, Bentgrass Drive, and Elbow Court in section “A,” including base repairs on Elbow Court.
  • Continuing with base repairs from the intersection of Up & Over Way, Bentgrass Drive, and Elbow Court in section “A” to the intersection of Bentgrass Drive & Plateau Drive in section “A,” including base repairs in Plateau Drive.
    • Per Harford County no base asphalt repairs are required in section “C” Gullwing Court.
  • Depending on how much time is left in the day, we anticipate backing up and starting surface paving in the very back section “D,” Bentgrass Drive.

November 12th

  • Complete surface paving in section “D” (Bentgrass Drive).
  • Surface pave Boomerang Way in section “A.”
  • Surface pave Elbow Court in section “A.”
  • Surface pave Gullwing Court in section “C.”
  • If there is enough time left in the day, we will back up and start surface paving from the intersection of Up & Over Way and Bentgrass Drive where sections “A,” “B,” and “D” all meet.

November 13th 

  • Continue to surface pave Up & Over Way to the intersection of Up & Over Way and Bentgrass Drive in section “A.”
  • Then surface pave Bentgrass from the intersection of Up & Over Way, Bentgrass Drive, and Elbow Court in section “A” to the intersection of Bentgrass Drive & Plateau Drive in section “A,” including Plateau Drive.

Note:

  • Lennar has allotted November 15th and 16th in their paving schedule to complete this roadway work due to any inclement weather or issues that may arise during this operation.
  • Lennar will be providing traffic control services at “all” times during this operation so please pay close attention to these folks who will be directing traffic.
  • DXI will be issuing flyers to all of the residents that will be impacted due to these operations. Flyers will go out Friday, November 5th.

We appreciate your cooperation and understanding. Thank you.